Burnup
This line represents the "total work" planned. Unlike other charts, this line is dynamic; it moves up if stakeholders add new requirements (scope creep) or down if tasks are removed. 2. Common "Burnup" Story Archetypes
The progress line stays flat for most of the project and then suddenly shoots up at the very end. This usually indicates a bottleneck where work is being done but isn't officially "Done" (perhaps waiting for testing or QA) until the last minute. burnup
This line tracks "work completed" and trends upward as the team reaches their "Definition of Done" for various tasks. This line represents the "total work" planned
The progress line moves at a consistent angle (velocity) and eventually meets the scope line exactly on the deadline. This is the story of a well-estimated, stable project. 3. How to Develop Your Story Common "Burnup" Story Archetypes The progress line stays
Depending on how these lines move, your burnup chart might tell one of these common project stories:
Your progress line is climbing steadily, but the scope line keeps jumping higher. This tells the story of a team working hard while stakeholders continuously add new features, making the "finish line" feel unreachable.